EV Charging Time & Cost Calculator — AC and DC

EV charging time and cost: onboard charger limit, 1- or 3-phase supply, US 80 % breaker rule, charging loss, DC taper past 80 %, off-peak rates, cost per 100 km or mi.

Live calculationWorking shown

EV charging · time and cost

How long the charge takes and what it costs

Where are you charging?
Driving and monthly cost (optional)

Charging time

5 h 02 min

20 % → 80 %: 36 kWh into the battery

  • Charging at 7.68 kW, limited by the charge point: 240 V × 32 A × 1 = 7.68 kW. A 40 A breaker allows 32 A of continuous charging (80 %).
  • From the grid: 38.71 kWh (2.71 kWh lost at 7 %)
  • Adds about 129 mi of driving
  • 30 kWh from the grid per 100 mi
  • 1,000 mi a month: 300 kWh
Compare with a petrol or diesel car over 1,000 mi

Opens the fuel cost calculator with this consumption and electricity price filled in; add the fuel car’s consumption and pump price there.

Working

  1. 60 kWh × (80 % − 20 %) ÷ 100 = 36 kWh into the battery
  2. Lowest of charge point 7.68 kW, circuit on the car’s phases 7.68 kW and car 11 kW = 7.68 kW
  3. 36 kWh ÷ (1 − 7 %) = 38.71 kWh from the grid
  4. 38.71 kWh ÷ 7.68 kW = 5 h 02 min
More actions

Shared links reopen these inputs. Recent and saved calculations stay in this browser unless you clear site data.

Runs in your browser. Nothing you enter is sent to MAXScanner.

Charging time from 20 % to 80 % by charge point

Hours and minutes for each usable capacity at the charge point’s full power, with the default loss for that power. A car whose onboard charger is smaller than the charge point charges at its own limit instead.

Charge pointPower40 kWh60 kWh80 kWh100 kWh
120 V · 12 A · single phase1.44 kW (15 %)19 h 36 min29 h 25 min39 h 13 min49 h 01 min
230 V · 10 A · single phase2.3 kW (15 %)12 h 17 min18 h 25 min24 h 33 min30 h 41 min
230 V · 16 A · single phase3.68 kW (10 %)7 h 15 min10 h 52 min14 h 30 min18 h 07 min
240 V · 32 A · single phase7.68 kW (7 %)3 h 22 min5 h 02 min6 h 43 min8 h 24 min
230 V · 32 A · single phase7.36 kW (7 %)3 h 30 min5 h 16 min7 h 01 min8 h 46 min
230 V · 16 A · three phase11.04 kW (7 %)2 h 20 min3 h 30 min4 h 41 min5 h 51 min
230 V · 32 A · three phase22.08 kW (7 %)1 h 10 min1 h 45 min2 h 20 min2 h 55 min

Worked examples from the calculator

Each row is the calculator’s own result with its default losses: 15 % below 3 kW, 10 % from 3 to 7 kW, 7 % above, 5 % on DC.

ScenarioPower and limitTimeFrom the grid
60 kWh, 20 → 80 %, 7.4 kW single-phase wallbox (230 V, 32 A), car with 11 kW onboard7.36 kW · charge point5 h 16 min38.71 kWh (7 %)
60 kWh, 20 → 80 %, 11 kW three-phase wallbox (230 V, 16 A), car with 11 kW onboard11 kW · car’s onboard charger3 h 31 min38.71 kWh (7 %)
60 kWh, 20 → 80 %, 22 kW three-phase wallbox (230 V, 32 A), car with 11 kW onboard11 kW · car’s onboard charger3 h 31 min38.71 kWh (7 %)
40 kWh, 20 → 80 %, 11 kW three-phase wallbox, car with a 7.4 kW single-phase charger3.68 kW · one phase only7 h 15 min26.67 kWh (10 %)
60 kWh, 20 → 80 %, US Level 2 at 240 V on a 40 A circuit, car with 11 kW onboard7.68 kW · charge point5 h 02 min38.71 kWh (7 %)
60 kWh, 20 → 80 %, household socket (230 V, 10 A)2.3 kW · charge point18 h 25 min42.35 kWh (15 %)
60 kWh, 10 → 100 %, 150 kW DC charger, car peak 130 kW130 → 13 kW · DC taper53 min (To 80 %: 27 min · from 80 % to 100 %: 27 min)56.84 kWh (5 %)
60 kWh, 10 → 80 %, 50 kW DC charger, car peak 130 kW50 → 50 kW · DC taper53 min44.21 kWh (5 %)

The DC taper the calculator assumes

Share of the car’s peak DC power at each charge level, straight lines between the points. A charger below the car’s peak caps the power until the car’s curve drops under it.

Charge levelShare of peak130 kW car on a 150 kW charger130 kW car on a 50 kW charger
0 %100 %130 kW50 kW
10 %100 %130 kW50 kW
20 %100 %130 kW50 kW
30 %100 %130 kW50 kW
40 %100 %130 kW50 kW
50 %85 %111 kW50 kW
60 %70 %91 kW50 kW
70 %55 %72 kW50 kW
80 %40 %52 kW50 kW
90 %25 %33 kW33 kW
100 %10 %13 kW13 kW

Sources: ADAC, Ladeverluste beim Elektroauto: Wie hoch sind sie wirklich? (August 6, 2026); U.S. DOE Alternative Fuels Data Center, Electric Vehicle Charging Stations (November 17, 2026); Fastned, Everything you always wanted to know about fast charging (November 17, 2026); Idaho National Laboratory, Cold temperatures slow EV fast charging (Motoaki, Yi & Salisbury, Energy Policy 122, 2018) (August 1, 2018); AAA, Electric Vehicle Range Testing (research report, 20 °F / 75 °F / 95 °F) (February 7, 2019). Read on November 17, 2026.

How the calculator works out time and cost

Charging time is the energy the battery needs divided by the power that actually reaches it. Taking a 60 kWh (usable) battery from 20 % to 80 % puts 36 kWh into it. On a 7.4 kW single-phase wallbox (230 V × 32 A) the meter records 38.71 kWh after a 7 % charging loss and the charge takes 5 h 16 min; at 11 kW three-phase it takes 3 h 31 min, and on a 2.3 kW household socket, where about 15 % is lost, 18 h 25 min. The power is the lowest of three limits: the charge point, the circuit on the phases the car can use, and the car’s onboard AC charger. That is why a 22 kW wallbox charges a car with an 11 kW onboard charger at 11 kW, and a car with a single-phase charger gets only 3.7 kW from a three-phase 16 A wallbox. For DC fast charging the calculator follows a stated taper curve and splits the time before and after 80 %. Add your price per kWh, an off-peak window or your monthly distance to get the cost per charge, per month and per 100 km or 100 miles, then compare it with a petrol or diesel car in the fuel cost calculator.

How to use this calculator

1

Pick an example car or enter your own: usable battery capacity, onboard AC charger power and the phases it uses, and peak DC power.

2

Set the charge level you start from and the level you want, for example 20 % to 80 %.

3

Choose AC or DC. For AC, pick your electricity supply and charge point, or enter volts, amps and phases; tick the breaker option when you enter a US circuit size.

4

Add your price per kWh, and for a two-rate tariff the off-peak price, its hours and the time you plug in.

5

Optionally enter the car’s consumption and your monthly distance for the cost per 100 km or 100 mi, then open the fuel cost calculator to compare with a petrol car.

Where people use it

  • •Checking whether a 7.4 kW, 11 kW or 22 kW wallbox makes any difference for your car before paying for the installation.
  • •Planning an overnight charge so it finishes inside the off-peak hours of your tariff.
  • •Estimating a fast-charging stop on a trip: 10 % to 80 % against 80 % to 100 %.
  • •Working out what an EV costs per month in electricity and comparing it with a petrol or diesel car.

Example: 60 kWh from 20 % to 80 % on a 7.4 kW wallbox

A car with 60 kWh usable and an 11 kW onboard charger is plugged into a single-phase wallbox (230 V, 32 A) at 18:00 with 20 % left. The battery needs 60 × (80 − 20) ÷ 100 = 36 kWh. The wallbox is the lowest limit at 230 × 32 = 7.36 kW, so with the default 7 % loss the meter records 36 ÷ 0.93 = 38.71 kWh and the charge takes 38.71 ÷ 7.36 = 5 h 16 min. At a flat 0.30 per kWh that is 11.61. On a two-rate tariff with 0.10 per kWh from 23:00 to 07:00 and 0.30 during the day, scheduling the charge to start at 23:00 ends it at 04:16 and costs 3.87; starting straight away at 18:00 costs 11.23, because only the last 1.91 kWh fall after 23:00.

What the estimate leaves out

  • •The DC curve is generic. Real cars hold their peak longer or shorter, and a charger’s rated power is only a ceiling: a charger sharing its power with a second car, or one limited by its maximum current, delivers less. When the car maker publishes a 10–80 % time, that figure beats this estimate.
  • •Battery temperature changes fast-charging time the most. A cold battery can take up to about three times as long (INL), and the cold-weather option shows that band; preheating the battery on the way to the charger avoids most of it.
  • •Two cars sharing one charge point, or a home load manager that turns the wallbox down while the oven is on, lower the power below what the calculator shows.
  • •On AC the last few percent can be slower than the rest while the car balances its cells; the calculator holds the AC power constant up to the target.
  • •Some cars with a three-phase charger draw only 16 A on a single phase (3.7 kW). If your manual says so, enter 3.7 kW as the onboard charger when you charge on one phase.
  • •Public chargers may add per-minute, session or idle fees to the price per kWh; the cost here is the energy only.
  • •Usable capacity is lower than the gross figure some brochures quote, and an older battery holds less. Energy the car uses for heating or cooling the cabin while plugged in is not included.

Frequently asked questions

How long does it take to charge an electric car at home?+

Divide the energy you need by the charging power. From 20 % to 80 %, a 60 kWh battery takes 36 kWh: about 18 h 25 min on a 2.3 kW household socket, 5 h 16 min on a 7.4 kW wallbox, 5 h 02 min on a US Level 2 charger on a 40 A circuit (7.68 kW) and 3 h 31 min at 11 kW, with the default losses of 15 % at the socket and 7 % at a wallbox. A US Level 1 outlet (120 V, 12 A, 1.44 kW) needs about 29 h 25 min for the same charge.

Is a 22 kW wallbox faster than an 11 kW one?+

Only when the car’s onboard charger accepts 22 kW. Many cars charge at no more than 11 kW on AC (some at 7.4 kW on one phase, a few at 22 kW), and the car never draws more than its own limit, so the same 36 kWh charge takes 3 h 31 min on both wallboxes. Check the AC charging power in the car’s data sheet before paying for a 22 kW installation.

Why does fast charging slow down after 80 %?+

The car’s battery management lowers the current as the cells approach full, to keep them from overheating; Fastned writes that the speed typically drops at 80–90 % and falls further towards 100 %. The calculator’s generic curve keeps the full peak to 40 %, then falls to 40 % of the peak at 80 % and 10 % at 100 %. On a 150 kW charger, a car with a 130 kW peak and 60 kWh usable needs about 27 min from 10 % to 80 % and another 27 min from 80 % to 100 %.

How much does it cost to charge an electric car?+

Energy from the grid × your price per kWh. The 38.71 kWh of a 20–80 % charge on a 60 kWh battery cost 11.61 at 0.30 per kWh and 3.87 at an off-peak 0.10. Per distance, an official consumption of 18 kWh/100 km at 0.30 per kWh is 5.40 per 100 km. WLTP and EPA figures are measured at the socket, so they already include the charging loss.

How much energy is lost while charging an EV?+

ADAC measured five cars in 2026: 5.1–7.0 % lost at an 11 kW wallbox, 8.0–12.8 % at about 4 kW and 12.7–15.3 % at a 2.3 kW household socket, where one car lost 24.2 %. On DC fast chargers 1–10 % was lost inside the car, more when it heated the battery, plus about 3 % in the station. The calculator uses 15 %, 10 % or 7 % by AC power and 5 % for DC unless you enter your own figure.

Does cold weather make EV charging slower?+

Yes for fast charging, much less at home. In an Idaho National Laboratory study of taxi sessions on a 50 kW charger, a battery at 0 °C (32 °F) gained about 36 % less charge in 30 minutes than at 25 °C, and in the coldest sessions charging was about three times slower. Preheating the battery before a fast charge avoids most of that, at a cost of 2–8 % extra energy in ADAC’s tests. AAA measured 12 % less range at −7 °C (20 °F) without cabin heating and 41 % less with it.

How many amps does a home EV charger need?+

In the US and Canada an EV charger is a continuous load, so it may draw at most 80 % of its breaker: 32 A on a 40 A circuit (7.68 kW at 240 V), 40 A on 50 A (9.6 kW) and 48 A on 60 A (11.52 kW). In Europe a 230 V single-phase 32 A circuit gives 7.4 kW and 16 A on three phases gives 11 kW. Your electrician and local rules decide the circuit; tick the breaker option in the calculator when you enter a breaker size.

Semantic next steps

Continue the calculation

These links move to a different input, formula or project stage rather than a keyword variation of this page.

Free publisher widget

Put this calculator on your website

Give readers the live calculator without rebuilding the math. Copy the responsive embed in one click, or customize width, height, border and corner radius before publishing. The branded MAXScanner attribution stays visible.

Preview

Calculator embed HTML

Paste this code into your page. Focus the code box to select it manually.

Keep the result connected to the real job

MAXScanner keeps the formula and assumptions beside the result so you can verify the number before using it in a drawing, estimate, specification, worksheet or document. Where a supplier, manufacturer, drawing or applicable standard owns a requirement, that source remains authoritative.