Concrete Mix Calculator: Cement, Sand & Aggregate

Cement bags, sand, coarse aggregate and water for M5–M25 nominal mixes (1:5:10 to 1:1:2) or your own ratio, in m³, ft³ and tonnes, with the IS 456 limits checked.

Live calculationWorking shown

Concrete mix calculator

Cement, sand and aggregate for your pour

Quantity of concrete
Dimensions in
Assumptions you can change

Turns wet concrete into loose dry ingredients. 1.54 is the common site value; some estimators use 1.52 or 1.57.

Spillage and uneven formwork. Leave at 0 if your volume already includes it.

IS 456 Table 5: at most 0.55 for reinforced concrete in mild exposure, 0.50 in moderate exposure.

Loose bulk densities. Cement 1,440 and dry sand 1,540–1,600 kg/m³ are from IS 875 (Part 1); ask your supplier for the stone.

Materials for 1.8 m³

Cement · 50 kg

15 bags

14.52 bags of 50 kg exactly · 725.8 kg of cement

Sand

0.756 m³ · 26.7 ft³

1,210 kg · 1.21 t

Coarse aggregate

1.512 m³ · 53.4 ft³

2,268 kg · 2.27 t

Water

363 litres

25 litres per 50 kg of cement

Within IS 456 Table 9 for M20: 239.6 kg of aggregate per 50 kg of cement (maximum 250 kg) and 25 litres of water (maximum 30).

How it was worked out
  1. 1 × 4 m × 3 m × 150 mm = 1.8 m³
  2. 1.8 m³ × 1.54 = 2.772 m³ of dry ingredients
  3. Cement: 2.772 × 1 ÷ 5.5 = 0.504 m³ × 1,440 kg/m³ = 725.8 kg ÷ 50 kg = 14.52 bags
  4. Sand: 2.772 × 1.5 ÷ 5.5 = 0.756 m³ × 1,600 kg/m³ = 1,209.6 kg
  5. Aggregate: 2.772 × 3 ÷ 5.5 = 1.512 m³ × 1,500 kg/m³ = 2,268 kg
  6. Water: 725.8 kg × 0.5 = 363 litres
More actions

Shared links reopen these inputs. Recent and saved calculations stay in this browser unless you clear site data.

Runs in your browser. Nothing you type is sent to a server.

Nominal mixes and the IS 456 limits

Per cubic metre of finished concrete with this page’s defaults (factor 1.54, 50 kg bags, sand 1,600 and aggregate 1,500 kg/m³). The last two columns compare the mix with IS 456:2000 Table 9, which sets the maximum aggregate per 50 kg of cement.

GradeSite ratioCement bags (50 kg)SandAggregateAggregate per 50 kg cementTable 9 maximum
M51:5:102.770.481 m³0.963 m³798.6 kg800 kg
M7.51:4:83.410.474 m³0.948 m³638.9 kg625 kg
M101:3:64.440.462 m³0.924 m³479.2 kg480 kg
M151:2:46.340.44 m³0.88 m³319.4 kg330 kg
M201:1.5:38.060.42 m³0.84 m³239.6 kg250 kg
M251:1:211.090.385 m³0.77 m³159.7 kgno nominal mix

With these densities 1:4:8 carries 639 kg of aggregate per 50 kg of cement, a little over the 625 kg that Table 9 allows for M7.5. If your mix must meet the table, use a little more cement or weigh the actual materials.

Why other calculators give different numbers

The same 1 m³ of M20 (1:1.5:3) with one assumption changed at a time. Most published answers differ because the factor, the wastage or the density is hidden.

AssumptionCement bags (50 kg)Sand (t)Aggregate (t)
Dry-volume factor 1.527.960.661.24
Dry-volume factor 1.54 (this page)8.060.671.26
Dry-volume factor 1.578.220.691.28
Factor 1.54 plus 5% wastage8.470.711.32
Factor 1.54, sand at 1,450 kg/m³8.060.611.26

The assumptions and where they come from

Dry-volume factor
1.54 (editable)Source: Site estimating convention; published values range from 1.52 to 1.57. Not set by any standard.
Cement bulk density
1,440 kg/m³, so a 50 kg bag is 0.0347 m³ (1.23 ft³)Source: IS 875 (Part 1):1987, Table 1
Sand bulk density
1,600 kg/m³ (dry, clean)Source: IS 875 (Part 1):1987, Table 1 gives 1,540–1,600 kg/m³ for dry clean sand
Coarse aggregate density
1,500 kg/m³ (loose 20 mm stone)Source: Typical value, not a code figure. Replace it with the supplier’s loose bulk density (tested to IS 2386 Part 3).
Water
water-cement ratio 0.50Source: IS 456:2000 Table 5 (maximum 0.55 mild, 0.50 moderate exposure, reinforced concrete) and Table 9 (litres per 50 kg of cement)
Nominal mix
M5 to M20 onlySource: IS 456:2000 clauses 9.1.1 and 9.3; design mix (IS 10262) above M20

IS 456 and IS 875 read on 12 November 2026 from the public text of the standards. Bag sizes are the everyday sizes sold in each market.

How the materials are worked out

One cubic metre of M20 concrete (1:1.5:3) needs about 8.06 bags of 50 kg cement (403 kg), 0.42 m³ of sand (672 kg) and 0.84 m³ of 20 mm aggregate (1,260 kg), plus 202 litres of water at a water-cement ratio of 0.50. Those figures come from the usual site method: multiply the wet volume by a dry-volume factor of 1.54, split the result by the mix parts, then convert cement to bags and sand and aggregate to tonnes with bulk densities. Every one of those assumptions is visible below and can be changed, and the result is checked against the aggregate and water limits of IS 456:2000 Table 9 for M5 to M20.

How to use this calculator

1

Enter the volume of concrete, or the length, width and thickness of the slab or footing.

2

Pick a grade (M5 to M25) to load its nominal ratio, or choose a custom cement : sand : aggregate ratio.

3

Choose the cement bag sold where you build: 50 kg, 40 kg, 25 kg, 20 kg or 94 lb.

4

Open the assumptions to change the dry-volume factor, wastage, water-cement ratio or densities, then read the bags, sand, aggregate and water with the working.

Where people use it

  • •Ordering cement, sand and aggregate for a roof slab, footing or floor that is mixed on site.
  • •Checking a contractor’s material estimate for a house extension.
  • •Converting a ratio such as 1:2:4 into bags and tonnes before visiting the supplier.
  • •Comparing how much cement a richer mix (M20 instead of M15) adds to the bill of materials.

Example: 4 m × 3 m slab, 150 mm thick, M20

The volume is 4 × 3 × 0.15 = 1.8 m³. The dry volume is 1.8 × 1.54 = 2.772 m³, and the parts add up to 1 + 1.5 + 3 = 5.5. Cement is 2.772 ÷ 5.5 = 0.504 m³, or 725.76 kg, which is 14.52 bags of 50 kg: buy 15. Sand is 0.756 m³ (1.21 tonnes) and aggregate 1.512 m³ (2.27 tonnes). At a water-cement ratio of 0.50 the mix takes about 363 litres of water. The mix carries 239.6 kg of aggregate per 50 kg of cement, within the 250 kg limit that IS 456 Table 9 sets for M20.

Where a nominal mix is not enough

  • •Nominal mixes are a fallback. IS 456:2000 prefers design mixes and allows nominal mixes only for M20 and lower, with the engineer’s permission. M25 at 1:1:2 is a site rule of thumb, not a code mix: structural concrete of M25 and above needs a design mix from a laboratory (IS 10262).
  • •The 1.54 factor is an estimating convention for voids between the dry ingredients, not a value from any standard; published figures use anything from 1.52 to 1.57. Wet sand bulks, so measure sand by mass or correct for moisture.
  • •Densities depend on the actual sand and stone. Replace the defaults with your supplier’s loose bulk density when you order by the tonne.
  • •Ready-mix concrete is ordered by the cubic metre or yard, not by ingredients. Use the concrete volume calculator for that, and this page only when you mix on site.

Frequently asked questions

How many bags of cement are needed for 1 m³ of M20 concrete?+

About 8.06 bags of 50 kg (403 kg) with the usual 1.54 dry-volume factor and a 1:1.5:3 mix, so buy 9 for one cubic metre. With a factor of 1.52 it is 7.96 bags and with 1.57 it is 8.22, which is why published answers range from 8 to 8.3.

How do I calculate cement, sand and aggregate for M20?+

Multiply the wet volume by 1.54 to get the dry volume, then divide it by the sum of the parts (1 + 1.5 + 3 = 5.5). Cement is 1 part, sand 1.5 parts and aggregate 3 parts of that. For 1 m³: cement 0.28 m³ (403 kg), sand 0.42 m³ and aggregate 0.84 m³.

Why is 1.54 used in concrete calculation?+

Dry cement, sand and aggregate take up more room loose than after mixing with water and compacting, because the finer particles fill the gaps between the coarser ones. Multiplying by 1.54 (sometimes 1.52 or 1.57) turns the finished volume back into the loose volume you have to buy. It is a rule of thumb; change it if your contractor uses another value.

What is the mix ratio of M5, M7.5, M10, M15, M20 and M25?+

The usual site ratios are 1:5:10 for M5, 1:4:8 for M7.5, 1:3:6 for M10, 1:2:4 for M15, 1:1.5:3 for M20 and 1:1:2 for M25. IS 456 itself specifies nominal mixes by mass, as the maximum aggregate per 50 kg of cement: 800, 625, 480, 330 and 250 kg for M5 to M20. It has no nominal mix for M25.

How much water is needed for one bag of cement?+

At a water-cement ratio of 0.50, one 50 kg bag takes 25 litres. IS 456 Table 9 caps the water per 50 kg of cement at 30 litres for M20, 32 for M15 and 34 for M10, and Table 5 caps the free water-cement ratio of reinforced concrete at 0.55 in mild exposure and 0.50 in moderate exposure.

How many bags of cement are in a cubic yard of concrete?+

For a 1:2:4 mix with the 1.54 factor, one cubic yard needs 242 kg of cement: 5.68 bags of 94 lb, so 6 bags. A richer 1:2:3 mix needs 6.63 bags. Bagged premixed concrete is different: use the yield printed on the bag.

Semantic next steps

Continue the calculation

These links move to a different input, formula or project stage rather than a keyword variation of this page.

Construction & DIY Calculators

Free publisher widget

Put this calculator on your website

Give readers the live calculator without rebuilding the math. Copy the responsive embed in one click, or customize width, height, border and corner radius before publishing. The branded MAXScanner attribution stays visible.

Preview

Calculator embed HTML

Paste this code into your page. Focus the code box to select it manually.

Keep the result connected to the real job

MAXScanner keeps the formula and assumptions beside the result so you can verify the number before using it in a drawing, estimate, specification, worksheet or document. Where a supplier, manufacturer, drawing or applicable standard owns a requirement, that source remains authoritative.